<back
|
Q. If you are not paid within 90 days after you record your mechanic's lien, have you filed suit?
|
 |
A. To enforce a mechanic's lien, you must file suit within 90 days of the day you recorded your mechanic's lien. You must also record a lis pendens on the property.
|
 |
Q. If you are not paid after you serve the Stop Notice, did you file suit?
|
 |
A. To collect on the Stop Notice, you must file suit within 90 days of the last day a Stop Notice may be filed. |
Note: If you are not the prime contractor, you must have given the preliminary notice.
II.
 |
Q. If you are a subcontractor on a PUBLIC WORKS PROJECT, is the contract with the federal government or a state or local government entity?
|
|
If your project is a PUBLIC WORKS PROJECT for a state agency or local entity, serve a 20 day Preliminary Notice as soon as you enter the contract or start work. |
 |
If your project is a public works project for a state agency or local entity, and you finished your job and payment to you is overdue, serve a Stop Notice on the Public Agency, and prime contractor. |
 |
If you are a subcontractor or material supplier you must serve your Stop Notice within 30 days of the day a Notice of Completion, Notice of Acceptance or Notice of Cessation is recorded. |
 |
If no Notice of Completion, Notice of Acceptance or Notice of Cessation was recorded, you have up to 90 days from the date work stopped on the project to serve your stop notice if you are a subcontractor or material supplier. |
 |
Q. If you are not paid after you serve the Stop Notice, did you file suit? |
 |
To collect on the Stop Notice, you must file suit within 90 days of the last day a Stop Notice may be filed. |
Note: A prime contractor can not use a Stop Notice on Public Works.
|
III. Often, Public Works Projects for state or local entities require a bond. To collect on the bond, follow the steps listed below:
|
If your project is a Public Works Project for a state agency or local entity, and you finished your job and payment to you is overdue, serve a Bond Notice on the owner, lender and general contractor within 90 days of the day you last furnished labor or material. |
 |
To collect on the bond, you must file suit within six months after the last day a Stop Notice must be filed. |
IV. Federal Projects require a bond. The bond is called a Miller Act Bond. The federal government does not allow mechanic's liens or Stop Notices. To collect on the Miller Act Bond, follow the steps listed below:
|
If your project is a Federal Project, and you were not paid, and you are not the general contractor or a first-tier subcontractor, give notice to the federal government that you worked on the project within 90 days of the day you last worked on the project. Give notice by personal service or registered mail. |
 |
If you are a general contractor or a first-tier subcontractor, you do not need to give the federal government notice that you worked on the project. |
|
Q. If you are a subcontractor or material supplier, your project is a federal public works project, and you did not receive payment after serving the notice, did you file suit?
|
 |
A. To collect on the Miller Act Bond, you must file suit between 90 days after you finished work on the project and one year after you finished work on the project. |
The material for this section provided courtesy of:
Abdulaziz & Grossbart 6454 Coldwater Canyon Avenue North Hollywood, CA 91606 (818) 760-2000 (213) 877-5776 (818) 760-3908 FAX
Abdulaziz & Grossbart has over 30 years of combined experience in construction law. The firm is well respected in the field of construction law and has been honored by their peers and the construction industry as well as legislative and regulatory bodies.
For More Information: BES Members may purchase:
CALIFORNIA CONSTRUCTION LAW 1995 Edition Compiled & Edited by Sam K. Abdulaziz
To obtain your copy, call BES today.
Note: This information is not intended to be legal advice. This information is not a substitute for legal advice. This information is provided for informational purposes only.

California's Prompt-Pay Statutes Provided courtesy of Sam K. Abdulaziz, Attorney at Law
As a result of the advocacy of subcontractor trade associations, with help from prime contractors, California now has a substantial body of law dealing with prompt payment. The prompt payment statutes are broken up into two different sections. One deals with private works of improvement and the other one deals with public works of improvement. The statutes deal with retention, and progress payments, as well as payments from the owner to the prime and the prime to the sub. Ahead, we will try to explain California's Prompt Pay Statutes.
-
- Private Works of Improvement
Owner to Prime With respect to private works of improvement, the owner must make progress payments to the prime contractor within 30 days after receipt of the request for payment unless this is modified in writing. If the owner does not, the owner is subjected to paying a penalty of 2% per month in lieu of interest. In addition, the prevailing party in litigation will be entitled to attorneys' fees. If there is a dispute over the amount of the payment, the owner may withhold up to 150% of the amount in dispute.
With respect to retention, the retention must be paid by the owner to the prime contractor within 45 days after a certificate of occupancy or 45 days after a notice of completion depending on when the contract was entered into.
Again, if the owner fails to pay, there is a 2% penalty per month. In addition, the prevailing party in litigation will be entitled to attorneys' fees. If there is a dispute over the amount of the payment, the owner may withhold up to 150% of the amount in dispute. With respect to retention, unlike progress payments, it is against public policy to waive this portion of the prompt pay statute. Therefore a waiver will probably not be upheld.
- Prime Contractors to Subcontractors With respect to progress payments, they must be made within 10 days of receipt of the funds by the contractor. Again, this can be modified by a written agreement. There is a 2% per month penalty in addition to interest for failure to comply and the payer can withhold up to 150% of the disputed amount. There is a provision allowing attorneys' fees to the prevailing party.
Retention must also be paid within 10 days after receipt from the owner. Again, there is a 2% per month penalty and the contractor can withhold no more than 150% of the disputed amount. There is a provision allowing attorneys' fees to the prevailing party. In this situation it is against public policy to waive the retention payments. Therefore, a contract that would waive that law would probably not be upheld.
In summary the law states that retention must be promptly paid regardless of the agreement of the parties. However, the payment of progress payments can be modified by the parties. In both instances the payer may withhold 150% of the disputed amount and is subject to a 2% per month penalty (in some instances you can also get interest) for failing to pay. In addition the prevailing party is entitled to attorneys' fees.
- Public Works (Other than Utilities)
State or Local Agency to Prime Contractor Progress payments must be made by the agency within 30 days of submission of a pay request. Interest in this case is 10% per year on the unpaid amount. With respect to state public works, this became effective on contracts entered into after January 1, 1991, and with respect to local agency public contracts, this became effective with respect to contracts entered into after January 1, 1993.
Retention to the prime contractor must be paid within 60 days after completion. Again, the owner can withhold only 150% of the disputed amount. There is a provision allowing attorneys' fees to the prevailing party. If the owner does not pay a valid progress payment request, there is a 2% per month penalty and this applies to contracts entered into after January 1, 1993.
-
- Prime Contractors to Subcontractors Progress payments must be paid within 10 days after receipt of the progress payment from the owner. In this case there is a 2% per month penalty and the statute is already in effect.
Retention must be paid within 10 days after receipt and there is a 2% per month penalty. There is a provision allowing attorneys' fees to the prevailing party.
-
- The material for this section provided courtesy of . . .
-
Abdulaziz & Grossbart 6454 Coldwater Canyon Avenue North Hollywood, CA 91606 (818) 760-2000 (213) 877-5776 (818) 760-3908 FAX
The information contained here should not be construed as a comprehensive overview of the law, and should not be a substitute for legal advice.

-
- Important Phone Numbers . . .
-
-
| Jurisdiction |
Building Department |
| Escalon |
(209) 838-3556 |
| Lathrop |
(209) 858-2860 |
| Lodi |
(209) 333-6714 |
| Manteca |
(209) 239-8416 |
| Ripon |
(209) 599-2108 |
| Stockton |
(209) 937-8561 |
| Tracy |
(209)831-4600 |
| |
|
| Calavaras County |
(209) 754-6390 |
| San Joaquin County |
(209) 468-3123 |
| Stanislaus County |
(209) 525-6557 |
| Tuolumne County |
(209) 533-5633 |
Powered by OnlineHostService
|